Building and Other Construction Workers Welfare Cess Rules

Section 4: Time and manner of collection

(1) The cess levied under sub-section (1) of section 3 of the Act shall be paid by an employer, within thirty days of completion of the construction project or within thirty days of the date on which assessment of cess payable is finalised, whichever is earlier, to the cess collector.
(2)Notwithstanding the provisions of sub-rule (1), where the duration of the project or construction work exceeds one year, cess shall be paid within thirty days of completion of one year from the date of commencement of work and every year thereafter at the notified rates on the cost of construction incurred during the relevant period.
(3)Notwithstanding the provisions of sub-rule (1) and sub-rule (2), where the levy of cess pertains to building and other construction work of a Government or of a Public Sector Undertaking, such Government or the Public Sector Undertaking shall deduct or cause to be deducted the cess payable at the notified rates from the bills paid for such works.
(4)Notwithstanding the provisions of sub-rule (1) and sub-rule (2), where the approval of a construction work by a local authority is required, every application for such approval shall be accompanied by a crossed demand draft in favour of the Board and payable at the station at which the Board is located for an amount of cess payable at the notified rates on the estimated cost of construction:
Provided that if the duration of the project is likely to exceed one year, the demand draft may be for the amount of cess payable on cost of construction estimated to be incurred during one year from the date of commencement and further payments of cess due shall be made as per the provisions of sub-rule (2). (5)An employer may pay in advance an amount of cess calculated on the
basis of the estimated cost of construction along with the notice of commencement of work under section 46 of the Main Act by a crossed demand draft in favour of the Board and payable at the station at which the Board is located:
Provided that if the duration of the project is likely to exceed one year, the demand draft may be for the amount of cess payable on cost of construction estimated to be incurred during one year from the date of such commencement and further payment of cess due shall be made as per the provisions of sub-rule (2). (6)Advance cess paid under sub-rules (3), (4) and (5), shall be adjusted in
the final assessment made by the Assessing Officer.